Retaining Wall - Close-out
Altocrete
Primary retaining wall and drainage work completed in 2025. Close-out work and wall grinding continuing into 2026-27. One stairwell remains closed pending final completion.
In Progress
Concrete curb replacement for the north lot. Approved at $17,515. Underway spring 2026. Asphalt work to follow once curbs are complete.
In Progress
Asphalt Replacement
Ronson
Full asphalt replacement carried from 2025-26. Budgeted at $68,200. Sequenced to begin after North Lot curb completion.
Pending - Post Curbs
Railing replacement or repair carried from 2025-26. Budgeted at $21,000. Quotes currently in progress.
Quotes In Progress
Wall Grinding
Contractor TBD
Late-season wall grinding estimated at approximately $8,200. Timing to be confirmed after curb and asphalt work concludes.
Late Season